Latest Inventions Pipelines PROCESS OF ERECTION OF PIPE-LINE, PROCESS OF DRAGGING- THROUGH OF PIPE-LINE WITH PROTECTIVE ENVELOPE AND FACILITY FOR ITS IMPLEMENTATION
PROCESS OF ERECTION OF
PIPE-LINE, PROCESS
OF DRAGGING- THROUGH OF PIPE-LINE WITH PROTECTIVE ENVELOPE AND FACILITY FOR ITS
IMPLEMENTATION
FIELD: underground construction, laying of
pipe-line under natural and artificial obstacles, water barriers included.
SUBSTANCE: task of process consists in provision for laying pipe-line both under
standard conditions and under artificial and natural obstacles, water barriers
included, in grounds containing boulders and other solid inclusions with
guaranteed preservation of pipe-line insulation, for conducting repairs or total
replacement of pipe-line. Process of erection of pipe-line includes construction
of mine shafts outside of limits of water barrier, in points of largest
aggregation of boulders and other solid inclusions. First tunnel is driven under
obstacle between mine shafts by means of shield complex, then inclined sections
of tunnel are driven from mine shafts up to exit to level of laying of
pipe-lines constructed by trench-free method. Points of match of section under
obstacle with inclined sections of tunnel are connected with the aid of insets.
In process of tunnel driving with the help of shield complex metal housing or
cast in-situ lining is erected inside which protective polymer tube and working
pipe-line are dragged jointly or separately. Centralizers for traction and
traction-distribution branch of cable are arranged inside polymer tube. After it
pipe-line is dragged through. On dragging of protective polymer tube and
pipe-line they left are freely laid one relative another. Auxiliary,
traction-distribution and traction winches and cone mechanism with guide roller
are employed in arrangement of centralizers. Centralizers are positioned in
trench chute. Loop formed by traction, traction-distribution branches of cable
is passed through guiding holes ( conduits ) of all centralizers and is linked
to cable of auxiliary winch. As loop is drawn by auxiliary winch centralizers
are fixed on traction- distribution branch of cable at calculated distances and
in this manner they are arranged along route of tunnel.
EFFECT: provision for
laying of pipe-lines under artificial and natural obstacles including water
barriers. 14 cl, 6 dwg
Semenov A.N., Timoshin
V.V., Gil'shtejn S.R., Panov V.I., Karanda G.M., Tolstov A.Ja., Maslovskij V.N.
Patent number: 2205923
Publishing date: July 29, 2003
To make the order on reception of the complete information under the invention, interesting for you
Back
|  |